If you want to achieve maximum results with minimum effort in a short period of time, and want to pass the Microsoft 070-576-VB exam. You can use ITCertKing's Microsoft 070-576-VB exam training materials. The training materials of ITCertKing are the product that through the test of practice. Many candidates proved it does 100% pass the exam. With it, you will reach your goal, and can get the best results.

ITCertKing is website that can take you access to the road of success. ITCertKing can provide the quickly passing Microsoft certification 070-576-VB exam training materials for you, which enable you to grasp the knowledge of the certification exam within a short period of time, and pass Microsoft certification 070-576-VB exam for only one-time.

Like the real exam, ITCertKing Microsoft 070-576-VB exam dumps not only contain all questions that may appear in the actual exam, also the SOFT version of the dumps comprehensively simulates the real exam. With ITCertKing real questions and answers, when you take the exam, you can handle it with ease and get high marks.

Exam Code: 070-576-VB
Exam Name: Microsoft (PRO: Designing and Developing Microsoft SharePoint 2010 Applications)
One year free update, No help, Full refund!
Total Q&A: 153 Questions and Answers
Last Update: 2014-02-24

Microsoft 070-576-VB authentication certificate is the dream IT certificate of many people. Microsoft certification 070-576-VB exam is a examination to test the examinees' IT professional knowledge and experience, which need to master abundant IT knowledge and experience to pass. In order to grasp so much knowledge, generally, it need to spend a lot of time and energy to review many books. ITCertKing is a website which can help you save time and energy to rapidly and efficiently master the Microsoft certification 070-576-VB exam related knowledge. If you are interested in ITCertKing, you can first free download part of ITCertKing's Microsoft certification 070-576-VB exam exercises and answers on the Internet as a try.

070-576-VB Free Demo Download: http://www.itcertking.com/070-576-VB_exam.html

NO.1 You are helping an organization’s executive team to design an automated approval process to
standardize certain documents. You have the following requirements:
The documents must be reviewed and approved by multiple teams in the approval chain.
.Each reviewer must provide feedback as part of completing a review.
.Each reviewer must either approve or reject the documents.
.After review, the document status must be changed; an e-mail must be generated to the
document author and the next reviewer in the approval chain; and a task should be created for
the next reviewer in the approval chain.
You must design a custom workflow solution for the document approval process on a
SharePoint 2010 site.What should the solution include?
A. an initiation form to collect the reviewer’s feedback and a Simple activity to approve and
reject the document
B. an association form to collect the reviewer’s feedback and a Composite activity to support
conditional activities such as approval and rejection
C. a task form to collect the reviewer’s feedback and a Composite activity to support
conditional activities such as approval and rejection
D. a task form to collect the reviewer’s feedback and a Simple activity to approve and reject
the document
Answer: C

Microsoft   070-576-VB   070-576-VB exam simulations   070-576-VB questions   070-576-VB braindump

NO.2 You are designing a SharePoint 2010 information architecture plan for a client that specifies
the mechanics of implementing content type change control.The requirements for the change
control plan specify that:
.Site managers can create site-specific content types based on the content types in the parent
site.
.Content types must not be overwritten when changes are made to parent site content types.
.Site managers can change child site content types.
You need to specify a content type change control plan that meets all these requirements.
Which approach should you recommend?
A. Direct the site manager to explicitly set the read-only property of the content type to True.
Direct the site collection manager to make the specified change required in the child site to the
content type at the site collection level.
B. Direct the site manager to explicitly set the read-only property of the content type to True.
Perform a push-down operation from the parent site to overwrite the required changes to the
read- only content types in all the child sites.
C. Define the content type as read-only at the child site level. Direct the site manager to
explicitly set the read-only property of the content type to False to make changes to the content
type. Then change the read-only property to True.
D. Define the content type as sealed. Direct the site manager to explicitly set the sealed
property of the content type to False to make changes to the content type. Then change the
sealed property of the content type to True.
Answer: C

Microsoft braindump   070-576-VB   070-576-VB

NO.3 You are designing a SharePoint 2010 feature. The feature includes a feature receiver that
executes code on activation and deactivation.The feature receiver code interacts with a Web
service, which could cause errors beyond your control.You need to ensure that the feature does
not activate or deactivate if the Web service causes an error.Which approach should you
recommend?
A. Wrap your code in a Try-Catch block. Log the error and issue another request to the Web
service in the Catch block.
B. Wrap your code in a Try-Catch block. Log the error and throw an exception in the Catch
block.
C. Wrap your code in a Try-Catch block. Only catch exceptions of type SPException.
D. Wrap your code in a Try-Finally block. Log any issues your code encounters in the Finally
block.
Answer: B

Microsoft   070-576-VB   070-576-VB exam   070-576-VB   070-576-VB test

ITCertKing offer the latest JN0-730 exam material and high-quality HP2-K36 pdf questions & answers. Our 74-325 VCE testing engine and MSC-431 study guide can help you pass the real exam. High-quality ADR-001 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/070-576-VB_exam.html

Exam 070-515-VB VCE

Have you signed up for Microsoft 070-515-VB exam? Will masses of reviewing materials and questions give you a headache? ITCertKing can help you to solve this problem. It is absolutely trustworthy website. Only if you choose to use exam dumps ITCertKing provides, you can absolutely pass your exam successfully. You spend lots of time on these reviewing materials you don't know whether it is useful to you, rather than experiencing the service ITCertKing provides for you. So, hurry to take action.

ITCertKing Microsoft 070-515-VB exam questions are compiled according to the latest syllabus and the actual 070-515-VB certification exam. We are also constantly upgrade our training materials so that you could get the best and the latest information for the first time. When you buy our 070-515-VB exam training materials, you will get a year of free updates. At any time, you can extend the the update subscription time, so that you can have a longer time to prepare for the exam.

Add ITCertKing's products to cart now! You will have 100% confidence to participate in the exam and disposably pass Microsoft certification 070-515-VB exam. At last, you will not regret your choice.

IT certification exam is very popular examination in the current society, especially in the IT industry. IT certification test qualification is widely recognized by the international community. Promotion, salary raise and improving your job skills, IT certification exam is your best choice. I believe that you must think so. Then, don't hesitate to take Microsoft 070-515-VB exam which is the most popular test in the recent. If you have no idea how to prepare the certification materials for the exam, ITCertKing serve you. ITCertKing can provide you with everything you need.

Let me be clear here a core value problem of ITCertKing. All Microsoft exams are very important. In this era of rapid development of information technology, ITCertKing just one of the questions providers. Why do most people to choose ITCertKing ? Because the ITCertKing exam information will be able to help you pass the test. It provides the information which is up to date. With ITCertKing Microsoft 070-515-VB test questions, you will become full of confidence and not have to worry about the exam. However, it lets you get certified effortlessly.

You can free download part of ITCertKing's practice questions and answers about Microsoft certification 070-515-VB exam online, as an attempt to test our quality. As long as you choose to purchase ITCertKing's products, we will do our best to help you pass Microsoft certification 070-515-VB exam disposably.

Exam Code: 070-515-VB
Exam Name: Microsoft (Web Applications Development with Microsoft VB.NET Framework 4 Practice Test)
One year free update, No help, Full refund!
Total Q&A: 114 Questions and Answers
Last Update: 2014-02-24

The training tools of ITCertKing contains exam experience and materials which are come up with by our IT team of experts. Also we provide exam practice questions and answers about the Microsoft 070-515-VB exam certification. Our ITCertKing's high degree of credibility in the IT industry can provide 100% protection to you. In order to let you choose to buy our products more peace of mind, you can try to free download part of the exam practice questions and answers about Microsoft certification 070-515-VB exam online.

070-515-VB Free Demo Download: http://www.itcertking.com/070-515-VB_exam.html

NO.1 You are implementing an ASP .NET Web site that will be accessed by an international
audience. The site contains global and local resources for display elements that must be
translated into the language that is selected by the user. You need to ensure that the
Label control named lblCompany displays text in the users selected language from the
global resource file. Which control markup should you use?
A. <asp:Label ID="lblCompany" runat="server"
meta:resourcekey="lblCompany" />
B. <asp:Label ID="lblCompany" runat="server" Text="meta:lblCompany.Text" />
C. <asp:Label ID="lblCompany" runat="server" Text="<%$
Resources:lblCompanyText %>" /> D. <asp:Label ID="lblCompany" runat="server"
Text="<%$ Resources:WebResources, lblCompanyText %>" />
Answer: D

Microsoft study guide   070-515-VB   070-515-VB   070-515-VB

NO.2 You have created an ASP .NET server control named ShoppingCart for use by other
developers. Some developers report that the ShoppingCart control does not function
properly with ViewState disabled. You want to ensure that all instances of the
ShoppingCart control work even if ViewState is disabled. What should you do?
A. Require developers to set EnableViewStateMac to true.
B. Store state in ControlState instead of ViewState.
C. Serialize the state into an Application state entry called "MyControl".
D. Require developers to change the session state mode to SQLServer.
Answer: B

Microsoft   070-515-VB   070-515-VB original questions   070-515-VB   070-515-VB

NO.3 You are developing an ASP .NET Web page that contains input controls, validation
controls, and a button named btnSubmit. The page has the following code-behind. (Line
numbers are included for reference only.)
01 Public Class _Default
02 Inherits System.Web.UI.Page
03
04 Protected Sub SaveToDatabase()
05
06 End Sub
07
08 Protected Sub btnSubmit_Click(ByVal sender As Object,
09 ByVal e As EventArgs) Handles btnSubmit.Click
10
11 End Sub
12
13 End Class
You need to ensure that all data that is submitted passes validation before the data is
saved in a database. What should you do?
A. Add the following method override.
Protected Overrides Sub OnInit(ByVal e As EventArgs) MyBase.OnInit(e)
If (Page.IsValid) Then Me.SaveToDatabase() End Sub
B. Add the following method override.
Protected Overrides Sub OnLoad(ByVal e As EventArgs) MyBase.OnLoad(e)
If (Page.IsValid) Then Me.SaveToDatabase() End Sub
C. Add the following method override.
Protected Overrides Sub OnPreRender(ByVal e As EventArgs)
MyBase.OnPreRender(e)
If(Page.IsValid) Then Me.SaveToDatabase() End Sub
D. Add the following code segment at line 10. If (Page.IsValid) Then
Me.SaveToDatabase()
Answer: D

Microsoft test questions   070-515-VB certification   070-515-VB   070-515-VB

NO.4 You are implementing an ASP .NET application that uses data-bound GridView controls
in multiple pages. You add JavaScript code to periodically update specific types of data
items in these GridView controls. You need to ensure that the JavaScript code can
locate the HTML elements created for each row in these GridView controls, without
needing to be changed if the controls are moved from one page to another. What should
you do?
A. Replace the GridView control with a ListView control.
B. Set the ClientIDMode attribute to Predictable in the web.config file.
C. Set the ClientIDRowSuffixattribute of each unique GridView control to a different
value.
D. Set the @ OutputCache directives VaryByControl attribute to the ID of the GridView
control.
Answer: B

Microsoft braindump   070-515-VB   070-515-VB   070-515-VB test

NO.5 You are creating an ASP .NET Web site. The site has a master page named
Custom.master. The code-behind file for Custom.master contains the following code
segment.
Partial Public Class Custom
Inherits System.Web.UI.MasterPage
Public Property Region As String
Protected Sub Page_Load(ByVal sender As Object,
ByVal e As System.EventArgs) Handles Me.Load
End Sub
End Class
You create a new ASP .NET page and specify Custom.master as its master page.
You add a Label control named lblRegion to the new page.
You need to display the value of the master pages Region property in lblRegion. What
should you do?
A. Add the following code segment to the Page_Load method of the page code-behind
file. Dim custom As Custom = Me.Parent lblRegion.Text = custom.Region
B. Add the following code segment to the Page_Load method of the page code-behind
file. Dim custom As Custom = Me.Master lblRegion.Text = custom.Region
C. Add the following code segment to the Page_Load method of the Custom.Master.vb
code- behind file. Dim lblRegion As Label = Page.FindControl("lblRegion")
lblRegion.Text = Me.Region
D. Add the following code segment to the Page_Load method of the Custom.Master.vb
code- behind file. Dim lblRegion As Label = Master.FindControl("lblRegion")
lblRegion.Text = Me.Region
Answer: B

Microsoft   070-515-VB   070-515-VB   070-515-VB

ITCertKing offer the latest 1z0-481 exam material and high-quality 000-781 pdf questions & answers. Our MSC-235 VCE testing engine and 3I0-012 study guide can help you pass the real exam. High-quality 000-652 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/070-515-VB_exam.html

Microsoft certification 070-511-VB exam training materials

To pass the Microsoft 070-511-VB exam is a dream who are engaged in IT industry. If you want to change the dream into reality, you only need to choose the professional training. ITCertKing is a professional website that providing IT certification training materials. Select ITCertKing, it will ensure your success. No matter how high your pursuit of the goal, ITCertKing will make your dreams become a reality.

IT certification candidates are mostly working people. Therefore, most of the candidates did not have so much time to prepare for the exam. But they need a lot of time to participate in the certification exam training courses. This will not only lead to a waste of training costs, more importantly, the candidates wasted valuable time. Here, I recommend a good learning materials website. Some of the test data on the site is free, but more importantly is that it provides a realistic simulation exercises that can help you to pass the Microsoft 070-511-VB exam. ITCertKing Microsoft 070-511-VB exammaterials can not only help you save a lot of time. but also allows you to pass the exam successfully. So you have no reason not to choose it.

If you buy ITCertKing's Microsoft certification 070-511-VB exam practice questions and answers, you can not only pass Microsoft certification 070-511-VB exam, but also enjoy a year of free update service. If you fail your exam, ITCertKing will full refund to you. You can free download part of practice questions and answers about Microsoft certification 070-511-VB exam as a try to test the reliability of ITCertKing's products.

Exam Code: 070-511-VB
Exam Name: Microsoft (TS:Windows Apps Dev w/Microsoft .NET Framework 4)
One year free update, No help, Full refund!
Total Q&A: 72 Questions and Answers
Last Update: 2014-02-24

Practice what you preach is the beginning of success. Since you have chosen to participate in the demanding IT certification exam. Then you have to pay your actions, and achieve excellent results. ITCertKing's Microsoft 070-511-VB exam training materials are the best training materials for this exam. With it you will have a key to success. ITCertKing's Microsoft 070-511-VB exam training materials are absolutely reliable materials. You should believe that you can pass the exam easily , too.

070-511-VB Free Demo Download: http://www.itcertking.com/070-511-VB_exam.html

NO.1 You are developing a Windows Presentation Foundation (WPF) application. You have
the following style defined in the app.xaml file.
<Style x:Key="btnItalic" x:Name="styIeItalic"
TargetType="{ x:Type Button}">
Setter Property="FontStyle" Value="Itallc"/> </Style>
You need to apply this style to a button named buttonl in the application at run time.
Which code segment should you use?
A. button1.Style = TryCast(Me.FindName("styleItallc"),Style)
B. button1.Style = TryCast(Me.FindName("btnItalic"), Style)
C. button1.Style =
TryCast(Me.FindResource("btnItalic"), Style)
D. button1.Style = TryCast(Me.FindResource("styleItalic"), Style)
Answer: C

Microsoft   070-511-VB study guide   070-511-VB   070-511-VB braindump

NO.2 You use Microsoft .NET Framework 4 to create a Windows Presentation Foundation
(WPF) application. You write the following code fragment.
<StackPanel TextBox.PceviewTextInput="StackPanel_PreviewTextInput">
<TextBox Name="TxtBoxA"/>
<TextBox Name-"TxtBoxB"/>
<TextBox Naroe-"TxtBoxC"/>
</StackPanel>
You create an event handler named StackPanel_PreviewTextInput. You also have a
collection of strings named Keywords. You need to ensure that TxtBoxA and TxtBoxB
do not contain any of the strings in the Keywords collections. Which code segment
should you use?
A. Private Sub StackPanel_PreviewTextInput(sender As Ctoject, e
AsTextCompositionEventArgs) Dim feSource As FrameworkElement = TryCast(sender,
FrameworkElement)
If feSource.Name - "TxtBoxA" OrElse feSource.Name - "TxtBoxB" Then
For Each keyword As String In Keywords
If e.Text.Contains(keyword) Then
B. Handled = False
Return End If Next
C. Handled = True
End If
End Sub
D. Private Sub StackPanel_PreviewTextInput(sender As Object e As
TextCompositionEventArgs) Dim feSource As FrameworkElement = TryCast(e.Source,
FrameworkElement)
If feSource.Name = "TxtBoxA" OrElse feSource.Name = "TxtBoxB" Then
For Each keyword As String In Keywords
If e.Text.Contains(keyword) Then e.HandledFalse Return
End If
Next
E. Handled = True
End If
End Sub
F. Private Sub StackPanel_PreviewTextInput(sender As Object, e As
TextCompositionEventArgs) Dim feSource As FrameworkElement = TryCast(sender,
FraroeworkElement)
If feSource.Name = "TxtBoxA" OrElse feSource.Name = "TxtBoxB" Then
For Each keyword As String In Keywords
If e.Text.Contains(keyword) Then e.Handled = True Return
End If
Next
G. Handled = False
End If
End Sub
H. Private Sub StackPanel_PreviewTextInput(sender As Ctoject, e As
TextCompositionEventArgs) Dim feSource As FrameworkElement = TryCast(e.Source,
FrameworkElement)
If feSource.Name = "TxtBoxA" OrElse feSource.Name = "TxtBoxB" Then
For Each keyword As String In Keywords
If e.Text.Contains(keyword) Then e.Handled = True
Return End If Next
I. Handled = False
End If
End Sub
Answer: D

Microsoft   070-511-VB demo   070-511-VB test answers

NO.3 You are developing a user control for a Windows Presentation Foundation (WPF)
application. The user control contains a button. Both the user control and the hosting
control must receive the button click event. You need to ensure that the user control
responds to the button click event before the hosting control responds to the event. What
should you do?
A. Use a bubbling routed event. In the button click event handler, set the Handled
property to True.
B. Use a bubbling routed event. In the button click event handler, set the Handled
property to False.
C. Use a standard Microsoft .NET event. Set the Handled property to True.
D. Use a tunneling routed event. Set the Handled property to False.
Answer: C

Microsoft test questions   070-511-VB exam   070-511-VB   070-511-VB original questions

ITCertKing offer the latest 000-283 exam material and high-quality 642-447 pdf questions & answers. Our 70-464 VCE testing engine and HP2-B111 study guide can help you pass the real exam. High-quality 1Z0-597 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/070-511-VB_exam.html

The best Microsoft certification MB3-701 exam training mode released

Do you want to attend Microsoft MB3-701 test? Are you worried about MB3-701 exam? You want to sign up for MB3-701 certification exam, but you are worried about failing the exam. Do you have such situations? Don't worry and sign up for MB3-701 exam. As long as you make use of ITCertKing certification training materials, particularly difficult exams are not a problem. Even if you have never confidence to pass the exam, ITCertKing also guarantees to pass MB3-701 test at the first attempt. Is it inconceivable? You can visit ITCertKing.com to know more details. In addition, you can try part of ITCertKing MB3-701 exam dumps. By it, you will know that the materials are your absolute guarantee to pass the test easily.

Are you racking your brains for a method how to pass Microsoft MB3-701 exam? Microsoft MB3-701 certification test is one of the valuable certification in modern IT certification. Within the last few decades, IT got a lot of publicity and it has been a necessary and desirable part of modern life. Microsoft certification has been well recognized by international community. So, most IT people want to improve their knowledge and their skills by Microsoft certification exam. MB3-701 test is one of the most important exams and the certificate will bring you benefits.

Now IT industry is more and more competitive. Passing Microsoft MB3-701 exam certification can effectively help you entrench yourself and enhance your status in this competitive IT area. In our ITCertKing you can get the related Microsoft MB3-701 exam certification training tools. Our ITCertKing IT experts team will timely provide you the accurate and detailed training materials about Microsoft certification MB3-701 exam. Through the learning materials and exam practice questions and answers provided by ITCertKing, we can ensure you have a successful challenge when you are the first time to participate in the Microsoft certification MB3-701 exam. Above all, using ITCertKing you do not spend a lot of time and effort to prepare for the exam.

ITCertKing has been to make the greatest efforts to provide the best and most convenient service for our candidates. High speed and high efficiency are certainly the most important points. In today's society, high efficiency is hot topic everywhere. So we designed training materials which have hign efficiency for the majority of candidates. It allows candidates to grasp the knowledge quickly, and achieved excellent results in the exam. ITCertKing's Microsoft MB3-701 exam training materials can help you to save a lot of time and effort. You can also use the extra time and effort to earn more money.

Exam Code: MB3-701
Exam Name: Microsoft (Microsoft GP 2013 Financials)
One year free update, No help, Full refund!
Total Q&A: 75 Questions and Answers
Last Update: 2014-02-24

MB3-701 Free Demo Download: http://www.itcertking.com/MB3-701_exam.html

NO.1 Which setup is required to create salesperson records?
A. Vendors
B. National accounts
C. Sales territories
D. Employees
Answer: C

Microsoft exam dumps   MB3-701   MB3-701   MB3-701   MB3-701 test questions   MB3-701

NO.2 You need finance charges to appear on customer statements.
What should you do? (Each correct answer presents part of the solution. Choose two.)
A. Run the receivables aging process.
B. Post the receivables finance charge batch.
C. Reconcile the outstanding document amounts.
D. Run the assess finance charge process.
Answer: B,D

Microsoft study guide   MB3-701   MB3-701 test   MB3-701   MB3-701
Explanation:
Ref:
http://www.dynamicsgpinsights.com/ 2012 / 07 / 03 /receivables-management-period-endclosing-in-dyn
amics-gp/

NO.3 Which is true when you create a refund check?
A. You must set up a customer/vendor relationship.
B. You must place the Sales document to be refunded on hold.
C. You can only create a refund check to the parent company if the customer is part of a National
Account.
D. You must set up customer Electronic Funds Transfer (EFT) information in the Customer Card.
Answer: A

Microsoft   MB3-701   MB3-701 certification   MB3-701   MB3-701   MB3-701 test answers

NO.4 What is the effect of placing a customer record on hold?
A. The customer record is inactivated automatically.
B. You can enter only customer payments for that customer.
C. A warning message appears when you enter a new sales transaction.
D. You cannot post new transactions for that customer.
Answer: C

Microsoft dumps   MB3-701   MB3-701   MB3-701 exam prep   MB3-701 original questions

NO.5 You set up a National Account.
Which two are true? (Each correct answer presents part of the solution. Choose two.)
A. Individual sales summary and demographic information about both the parent customer and the
associated child customers are retained in Dynamics tables.
B. You can combine all sales transaction activity for both the parent customer and associated child
customers into one statement.
C. You can enter a cash receipt for the child customer and apply the receipt to the parent customer.
D. If you delete the parent customer, the associated child customers are deleted also.
Answer: C,D

Microsoft exam   MB3-701   MB3-701 answers real questions   MB3-701 exam   MB3-701

NO.6 You enter a transaction in the Receivables module.
You need to apply the entry to a Receivables document that was posted previously.
Which two document types should you use? (Each correct answer presents a complete solution.
Choose two.)
A. Credit Memos
B. Warranties
C. Returns
D. Debit Memos
Answer: A,C

Microsoft   MB3-701 demo   MB3-701 exam prep   MB3-701
Explanation:
Ref: https://community.dynamics.com/gp/f/ 32 /p/106116 / 207506.aspx#.Uf-Fz0HvvUl

NO.7 Which condition must be met in order to void a receivables cash receipt?
A. The cash receipt must be in the open file.
B. The cash receipt must be fully applied to one or more invoices.
C. The cash receipt must not be posted.
D. The cash receipt must be on hold-
Answer: A

Microsoft answers real questions   MB3-701 questions   MB3-701 braindump   MB3-701 certification training

NO.8 Which two processes can you perform in Paid Sales Transaction Removal? (Each correct
answer presents part of the solution, Choose two.)
A. Delete inactive customers.
B. Transfer sales commissions to employees.
C. Consolidate balance forward accounts.
D. Transfer fully applied transactions to history.
Answer: C,D

Microsoft demo   MB3-701 pdf   MB3-701   MB3-701
Explanation:
Ref:
http://www.dynamicsgpinsights.com/ 2012 / 07 / 03 /receivables-management-period-endclosing-in-dyn
amics-gp/

ITCertKing offer the latest 000-N37 exam material and high-quality 70-465 pdf questions & answers. Our 74-409 VCE testing engine and 70-460 study guide can help you pass the real exam. High-quality NS0-156 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/MB3-701_exam.html

Microsoft certification 74-343 the latest examination questions and answers come out

ITCertKing is an excellent source of information on IT Certifications. In the ITCertKing, you can find study skills and learning materials for your exam. ITCertKing's Microsoft 74-343 training materials are studied by the experienced IT experts. It has a strong accuracy and logic. To encounter ITCertKing, you will encounter the best training materials. You can rest assured that using our Microsoft 74-343 exam training materials. With it, you have done fully prepared to meet this exam.

Working in IT industry, IT people most want to attend Microsoft certification exam. As a widely recognized certification examination, Microsoft certification exams are becoming more and more popular. Among them, Microsoft 74-343 certification test is the most important exam. Having 74-343 certificate proves you have high skills. Owing to its importance, it is very difficult to pass Microsoft 74-343 exam successfully. Although to pass the exam is hard, you also don't need to worry about it. ITCertKing exam dumps will help you sail through 74-343 test.

Using ITCertKing you can pass the Microsoft 74-343 exam easily. The first time you try to participate in Microsoft 74-343 exam, selecting ITCertKing's Microsoft 74-343 training tools and downloading Microsoft 74-343 practice questions and answers will increase your confidence of passing the exam and will effectively help you pass the exam. Other online websites also provide training tools about Microsoft certification 74-343 exam, but the quality of our products is very good. Our practice questions and answers have high accuracy. Our training materials have wide coverage of the content of the examination and constantly update and compile. ITCertKing can provide you with a very high accuracy of exam preparation. Selecting ITCertKing can save you a lot of time, so that you can get the Microsoft 74-343 certification earlier to allow you to become a Microsoft IT professionals.

If you are looking for a good learning site that can help you to pass the Microsoft 74-343 exam, ITCertKing is the best choice. ITCertKing will bring you state-of-the-art skills in the IT industry as well as easily pass the Microsoft 74-343 exam. We all know that this exam is tough, but it is not impossible if you want to pass it. You can choose learning tools to pass the exam. I suggest you choose ITCertKing Microsoft 74-343 exam questions and answers. I suggest you choose ITCertKing Microsoft 74-343 exam questions and answers. The training not only complete but real wide coverage. The test questions have high degree of simulation. This is the result of many exam practice. . If you want to participate in the Microsoft 74-343 exam, then select the ITCertKing, this is absolutely right choice.

Exam Code: 74-343
Exam Name: Microsoft (Managing Projects with Microsoft Project 2013)
One year free update, No help, Full refund!
Total Q&A: 101 Questions and Answers
Last Update: 2014-02-24

74-343 Free Demo Download: http://www.itcertking.com/74-343_exam.html

NO.1 You are a resource manager who uses Project Standard 2013. You manage all of your
resources in a single plan, which acts as a Shared Resource Pool for other projects in your
organization. Each resource needs to pass an annual exam in order to work on construction sites.
You need to set up a method that allows you to pick the renewal month for each resource. What
should you do?
A. Rename the Resource Text1 Custom field to Exam Expiration Date. Enter the month when the
exam expires. Select the correct expiration date for each resource.
B. Use the Organizer to copy the Resource Finish1 Custom field from the Global.mpt. Select the
correct expiration date for each resource.
C. Rename the Resource Date1 Custom field to Exam Expiration Date. Create a Lookup table with
values containing the last date of each month. Select the correct expiration date for each exam.
D. Rename the Resource Month1 Custom field to Exam Expiration Date. Create a Lookup table with
monthly values. Select the correct expiration month for each exam.
E. Rename the Resource Flag1 Custom field to Exam Expired Date. Enter the expiration dates into a
Lookup table. Select the correct expiration date for each resource.
Answer: C

Microsoft   74-343   74-343

NO.2 You are a project manager who uses Project Standard 2013. You have been told to build
multiple project files for a program. You need to have all of your projects start with auto scheduled
tasks by default. What should you do?
A. Under schedule options, set New tasks created to Auto Scheduled for each project.
B. Use the Task Mode field to change the first task to Auto Schedule, then copy down for all of your
tasks.
C. Under schedule options, set New tasks created to Auto Scheduled for all new projects.
D. Highlight all of the tasks in your schedule and select the Auto Schedule button.
Answer: C

Microsoft exam dumps   74-343 questions   74-343 exam simulations   74-343 certification   74-343 practice test

NO.3 You are a project manager, and your organization uses Project Professional 2013.
You have created a detailed project schedule and have identified two tasks that are causing your
resource to be overallocated.
You need to use the Team Planner to reassign these
tasks from the overallocated resources to underallocated resources with the same skill set. What
should you do?
A. Right-click the task and reassign it to the underallocated resource.
B. Drag the underallocated resource on the task to reassign it.
C. Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.
D. Right-click the resource and reassign it to the underallocated resource.
Answer: A

Microsoft   74-343   74-343   74-343 questions   74-343 dumps

NO.4 You are a senior project manager, and your organization uses Project Standard 2013. You are
managing a large ERP project with both part-time and full-time resources. The part-time resources
have strict contractual limitations regarding working days and hourly availability. You need to make
sure the tasks for your part-time resources are only scheduled in the calendar during their
agreed-upon working days and hours.
What should you do?
A. Change the part-time resources' tasks to manually scheduled to ensure the dates do not go past
the agreed-upon terms of their contract.
B. Enter the availability start and end dates for each resource and change the percent of units to the
agreed-upon amount in their contract.
C. Enter the availability start and end dates for each resource and change the working time for each
resource to only include days and hours agreed upon in their contract.
D. Change the part-time resources' units to the percentage they are available and set task
constraints to must finish on to ensure the dates do not go past the agreed- upon terms of their
contract.
Answer: C

Microsoft   74-343 original questions   74-343 pdf   74-343 test questions   74-343

NO.5 You are a project manager for a software development company. You use Project Professional
2013.
You manage an integration project, and you discover that you need to add additional resources to
the integration tasks in order to meet your development complete milestone date.
The project is behind schedule, so you must shorten the duration of the integration development
work.
You identify two additional resources to work on the integration task.
When you add these resources, your task now shows it will complete three days ahead of schedule,
which leaves a contingency window for issues that may arise. In order to shorten the duration of the
task when the resources are added, you need to set the task type before adding the resources.
What should you do?
A. Use an automatically scheduled task and set the task type to fixed duration.
B. Use a manually scheduled task and set the task type to fixed work.
C. Use an automatically scheduled task and set the task type to fixed work.
D. Use a manually scheduled task and set the task type to fixed duration.
Answer: C

Microsoft   74-343   74-343 demo

NO.6 You are a project manager who uses Project Standard 2013.
You are creating a preliminary project schedule and are estimating the number of resources
required prior to finalizing the schedule.
You do not have named resources to complete the tasks, but you know the resource roles that are
necessary. One of the roles needed is architect.
You need to estimate how many architect hours are required to complete the work. What should
you do?
A. Add a Material Resource named architect.
B. Add a Budget Resource named architect.
C. Add a Work Resource named architect,
D. Add a Cost Resource named architect.
Answer: C

Microsoft test questions   74-343   74-343

NO.7 Your company uses Project Professional 2013. You are setting up a preliminary schedule by
using manually scheduled tasks. You create a task with no duration, start, or finish date, and then
you assign a resource. Later, you enter a duration of three days for that task. You need to let the
resource know how the Work will be affected. What should you say?
A. Work will increase to 24 hours.
B. Work will remain at 0 hours.
C. Work will increase to 16 hours.
D. Work will remain at 8 hours.
Answer: A

Microsoft   74-343   74-343   74-343

NO.8 You are a project manager, and you successfully complete a server consolidation project for
one of your data centers. You use Project Standard 2013 to plan and track the work. Your manager
wants you to begin similar projects on two other data centers. You need to create a template based
on the plan you used to manage the first data center consolidation project. You need to ensure that
the template has all baseline and actual data values removed. What should you do?
A. Within Microsoft Windows Explorer, create a copy of the original project plan and rename the
file type from .mpp to .mpt.
B. Open the plan and use the Move Project button to set the start date to the start of the new
project. Save the project file as Template.mpp.
C. Open the plan and reset the percent complete for each task to 0. Save the file as Template.mpp.
D. Open the plan and save the plan as a Project Template.
E. Open the plan, and copy and paste all of the task information into a new plan. Save the plan as a
Project Template.
Answer: D

Microsoft demo   74-343 certification   74-343 certification training   74-343

NO.9 You are a project manager who uses Project Professional 2013. You work on a construction
project that requires propane as a fuel source for your equipment. The foreman requires that you
enter project costs associated with all work completed on your project. The propane costs $5.00 per
gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee
of $20. You need to enter the propane costs into your project schedule prior to filling the propane
tank for the first time. What should you do?
A. Create a material resource with a material label of gallons. Enter $20 in the cost per use and
$5.00 in the standard rate.
B. Create a cost resource, add the resource to a task, and enter $25 in the actual cost.
C. Create a material resource with a material label of gallons. Enter $20 in the standard rate and
$5.00 in the cost per use.
D. Create a cost resource, add the resource to a task, and enter $2520 in the actual cost.
Answer: B

Microsoft dumps   74-343   74-343

NO.10 You are project manager who uses Project Professional 2013. Your organization uses Microsoft
SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project.
The task list contains over 100 items. You need to create a project based on the tasks in the
SharePoint list in the most efficient manner. What should you do?
A. Export the tasks into Microsoft Excel and then import the Excel file into Project Professional 2013.
B. Edit the Project Summary Task hyperlink column to point to the SharePoint task list and click the
Import button.
C. Open the tasks directly from the SharePoint site into Project Professional 2013.
D. Copy and paste the tasks from SharePoint into Project Professional 2013.
Answer: C

Microsoft dumps   74-343 study guide   74-343 exam simulations   74-343   74-343 test questions

NO.11 Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a
very complex project with over 100 resources. You need to ensure that all tasks are assigned to
resources. What should you do?
A. Use Task Usage view and look for Unassigned tasks.
B. Use Resource Graph view and look for the Unassigned resource name.
C. Use Resource Usage view and look for the Unassigned resource name.
D. Use Resource Sheet view and look for Unassigned tasks.
Answer: C

Microsoft original questions   74-343   74-343 test questions

NO.12 Your organization uses Project Professional 2013.
A senior stakeholder in a project asks you to determine when a task is over budget by comparing
the baseline cost of a task to the cost.
Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost
is greater than the cost.
You write a formula to display the indicator, but it only displays for normal tasks and not for
summary tasks.
You need to make the indicator display for summary tasks. Which two actions should you perform?
(Each correct answer presents part of the solution. Choose two.)
A. Within the Custom Field, set Calculation for task and group summary rows to Use Formula.
B. Within the Custom Field, set Calculation for task and group summary rows to Maximum.
C. Within the Graphical Indicators dialog box, check the Import Indicator Criteria button.
D. Within the Graphical Indicators dialog box, check Summary rows inherit criteria from
nonsummary row.
Answer: A,D

Microsoft practice test   74-343   74-343

NO.13 You are managing a project using Project Professional 2013.
Your project schedule is showing task overallocation indicators in the Gantt chart view.
You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details
for BA1 to understand their current workload before making any assignment changes. What should
you do?
A. Click the BA1 resource and scroll to the end of the project.
B. Click View, check Details, select Resource Form then click on the BA1 resource.
C. Click View, check Details, select Task Form then click on the BA1 resource.
D. Right-click the BA1 resource and select Information.
Answer: B

Microsoft test questions   74-343 exam simulations   74-343 exam   74-343   74-343 answers real questions

NO.14 Your organization uses Project Professional 2013 and records actual hours worked on the
project.
You manage a small e-commerce website implementation project.
One of your testers asks for assistance in completing a critical task, and you find two additional
testing resources that can assist with executing the critical test cases.
The total estimated work for the effort-driven task is 100 hours. The original testing resource,
Resource1, completes 25 hours of work on the task. You need to add Resource2 and Resource3 to
the task and split the remaining hours across all three resources now working on the task. Which
two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Open the Task Form and format it to show Work Details. Enter 25 hours of actual work for
Resource1. Then save the changes.
B. Open the Task Form and format it to show Work Details. Enter 75 hours of remaining work for the
assigned resource. Then save the changes.
C. Assign Resource2 and Resource3 to the task. Then save the changes.
D. Open the Task Form and format it to show Work Details. Enter 33.33 hours of work for each
resource. Then save the changes.
Answer: A, C

Microsoft   74-343 test   74-343 exam prep

NO.15 You are a program manager who uses Project Professional 2013. You manage a portfolio of
projects for a large point of sale implementation. All of your project managers have created
individual project schedules. You discover that you have resource constraints since multiple
resources are working on multiple projects. You need visibility into resources across all projects so
that you can most efficiently manage the resources and their availability. What should you do?
A. Create a shared resource pool and send the location to each project manager. Open the
individual project and the resource pool. From the individual project, select Resource Pool, Share
Resources, and choose Use Resources.
B. Create a shared resource pool and send the location to each Project Manager. Open the
individual project, select Resource Pool, Share Resources, and choose Use Resources.
C. Create a master resource list and send it to each project manager. Open the individual project and
copy and paste it into the Resource Sheet.
D. Create a master resource list and send it to each project manager. Open the individual project,
select Team Planner, and add the resources.
Answer: A

Microsoft pdf   74-343 dumps   74-343 exam prep

ITCertKing offer the latest MB6-889 exam material and high-quality 700-410 pdf questions & answers. Our 156-315.13 VCE testing engine and 00M-663 study guide can help you pass the real exam. High-quality 000-652 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/74-343_exam.html

070-492 latest dumps

Let me be clear here a core value problem of ITCertKing. All Microsoft exams are very important. In this era of rapid development of information technology, ITCertKing just one of the questions providers. Why do most people to choose ITCertKing ? Because the ITCertKing exam information will be able to help you pass the test. It provides the information which is up to date. With ITCertKing Microsoft 070-492 test questions, you will become full of confidence and not have to worry about the exam. However, it lets you get certified effortlessly.

About the materials that relate to Microsoft 070-492 exam, many websites can offer the exam materials. But these websites can't guarantee the quality of the exam dumps, meanwhile when you fail the exam, they can't also give you FULL REFUND guarantee. Compared with common reference materials, ITCertKing Microsoft 070-492 certification training materials is the tool that worth your use. With the help of ITCertKing Microsoft 070-492 real questions and answers, you can absolutely well prepare for the exam and pass the exam with ease. If you want to great development in IT industry, you need to take IT certification exam. If you want to pass your IT certification test successfully, it is necessary for you to use ITCertKing exam dumps.

Exam Code: 070-492
Exam Name: Microsoft (Upgrade your MCPD: Web Developer 4 to MCSD: Web Applications)
One year free update, No help, Full refund!
Total Q&A: 132 Questions and Answers
Last Update: 2014-02-24

In recent years, many people are interested in Microsoft certification exam. So, Microsoft 070-492 test also gets more and more important. As the top-rated exam in IT industry, 070-492 certification is one of the most important exams. With 070-492 certificate, you can get more benefits. If you want to attend the exam, ITCertKing Microsoft 070-492 questions and answers can offer you convenience. The dumps are indispensable and the best.

Microsoft 070-492 exam is very popular in IT field. Having 070-492 certificate is the best for those people who want to be promoted and is also a valid selection. And with the aid of 070-492 certification test, you can improve your skills and master some useful techniques in your job so that you can finish your work better and demonstrate your great ability before other people. Only in this way can you get more development opportunities.

Would you like to pass Microsoft 070-492 test and to get 070-492 certificate? ITCertKing can guarantee your success. When you are preparing for 070-492 exam, it is necessary to learn test related knowledge. What's more important, you must choose the most effective exam materials that suit you. ITCertKing Microsoft 070-492 questions and answers are the best study method for you. The high quality exam dumps can produce a wonderful effect. If you fear that you cannot pass 070-492 test, please click ITCertKing.com to know more details.

ITCertKing is a website to achieve dreams of many IT people. ITCertKing provide candidates participating in the IT certification exams the information they want to help them pass the exam. Do you still worry about passing Microsoft certification 070-492 exam? Have you thought about purchasing an Microsoft certification 070-492 exam counseling sessions to assist you? ITCertKing can provide you with this convenience. ITCertKing's training materials can help you pass the certification exam. ITCertKing's exercises are almost similar to real exams. With ITCertKing's accurate Microsoft certification 070-492 exam practice questions and answers, you can pass Microsoft certification 070-492 exam with a high score.

070-492 Free Demo Download: http://www.itcertking.com/070-492_exam.html

NO.1 You are developing an ASP .NET MVC web application for viewing a list of contacts. The
application is designed for devices that support changes in orientation, such as tablets and
smartphones. The application displays a grid of contact tiles in portrait mode.
When the orientation changes to landscape, each tile in the grid expands to include each contact's
details. The HTML that creates the tiled interface resembles the following markup.
The CSS used to style the tiles in landscape mode is as follows.
If this CSS is omitted, the existing CSS displays the tiles in portrait mode.
You need to update the landscape-mode CSS to apply only to screens with a width greater than or
equal to 500 pixels.
Which code segment should you use?
A. @media screen and (width >= 500px) {
. . .
}
B. @media screen and (min-width: 500px) {
. . . }
C. @media screen (min-width: 500px, max-width: 1000px) {
. . .
}
D. @media resolution (min-width: 500px) {
. . .
}
Answer: B

Microsoft   070-492 braindump   070-492 study guide

NO.2 You are designing a distributed application that runs on the Windows Azure platform.
The application must store a small amount of insecure global information that does not change
frequently.
You need to configure the application to meet the requirements.
Which server-side state management option should you use? (Each correct answer presents a
complete solution. Choose all that apply.)
A. Windows Azure application state
B. Sql Azure
C. Profile properties of the Windows Azure application
D. Windows Azure session state
Answer: B,D

Microsoft   070-492   070-492   070-492 certification training
Explanation:
SQL Database provides a relational database management system for Windows Azure and is based
on SQL Server technology. With a SQL Database instance, you can easily provision and deploy
relational database solutions to the cloud, and take advantage of a distributed data center that
provides enterprise-class availability, scalability, and security with the benefits of built-in data
protection and self-healing.
Session States in Windows Azure. If you are a Web developer, you are probably very familiar with
managing user state - that is you are familiar with tracking user activity and actions across several
request-response exchanges that occur in Web applications. Since HTTP is a stateless protocol,
developers over the years have developed all sorts of means to manage state. You'll even find an
MSDN page providing alternatives and recommendations for state management here. Cookies,
hidden fields, and query strings are some client-side options to tracking user state. When it comes
to managing that state on the server-side, most Web developers rely on session objects.

NO.3 You are designing an HTML5 website.
You need to design the interface to make the content of the web page viewable in all types of
browsers, including voice recognition software, screen readers, and reading pens.
What should you do? (Each correct answer presents a complete solution. Choose all that apply.)
A. Annotate HTML5 content elements with Accessible Rich Internet Application (ARIA) attributes.
B. Convert HTML5 forms to XForms.
C. Ensure that HTML5 content elements have valid and descriptive names.
D. Use HTML5 semantic markup elements to enhance the pages.
E. Use Resource Description Framework (RDF) to describe content elements throughout the entire
page.
Answer: A,D

Microsoft   070-492 answers real questions   070-492 certification

NO.4 You are authoring unit tests.
The unit tests must test code that consumes sealed classes.
You need to create, maintain, and inject dependencies in the unit tests.
Which isolation method should you use?
A. T4 text templates and code generation
B. Stub types
C. Shim types
D. Hard-coded implementation
Answer: C

Microsoft   070-492   070-492 certification

NO.5 You are developing an ASP .NET MVC application. The application is deployed in a web farm
and is accessed by many users.
The application must handle web server failures gracefully. The servers in the farm must share the
state information.
You need to persist the application state during the session.
What should you implement?
A. A state server
B. Cookieless sessions
C. A web garden on the web servers
D. An InProc session
Answer: A

Microsoft certification training   070-492   070-492 certification   070-492

NO.6 You are developing an ASP .NET MVC web application in Visual Studio 2012. The application
requires several thousand content files. All content is hosted on the same IIS instance as the
application.
You detect performance issues when the application starts.
You need to resolve the performance issues.
What should you do?
A. Implement HTTP caching in the ASP .NET MVC controllers.
B. Combine the content files by using ASP .NET MVC bundling.
C. Install a second IIS instance.
D. Move the content to a Windows Azure CDN.
Answer: B

Microsoft   070-492   070-492   070-492   070-492

NO.7 You are developing an ASP .NET MVC news aggregation application that will be deployed to
servers on multiple networks.
The application must be compatible with multiple browsers. A user can search the website for news
articles. You must track the page number that the user is viewing in search results.
You need to program the location for storing state information about the user's search.
What should you do?
A. Store search results and page index in Session.
B. Use Application state to store search terms and page index.
C. Use QueryString to store search terms and page index.
D. Store search results and page index in TempData
Answer: C

Microsoft   070-492 braindump   070-492 certification training

NO.8 DRAG DROP
You are developing an ASP .NET MVC web application in Visual Studio 2012.
The application has a model named ReservationLocation that contains properties named City and
State.
The view that displays reservations has a single text box named loc for entering the location
information. The location is entered as city, state.
There are action methods that have ReservationLocation as a parameter type. You need to ensure
that the City and State properties are correctly populated.
How should you implement model binding for the ReservationLocation type? (To answer, drag the
appropriate code segment to the correct location or locations. Each code segment may be used
once, more than once, or not at all. You may need to drag the split bar between panes or scroll to
view content.)
Answer:

NO.9 You are developing an ASP .NET MVC application that displays stock market information.
The stock market information updates frequently and must be displayed in real-time.
You need to eliminate unnecessary header data, minimize latency, and transmit data over a
full-duplex connection.
What should you do?
A. Implement long-running HTTP requests.
B. Instantiate a MessageChannel object on the client.
C. Implement WebSockets protocol on the client and the server.
D. Configure polling from the browser.
Answer: C

Microsoft   070-492 practice test   070-492   070-492   070-492 certification

NO.10 You are developing an ASP .NET MVC application.
You need to authenticate clients by using NT LAN Manager (NTLM).
Which authentication method should you implement?
A. Basic
B. Windows
C. Forms
D. Kerberos
Answer: B

Microsoft exam prep   070-492 practice test   070-492   070-492 dumps

NO.11 You are testing an ASP .NET application.
The test plan requires that tests run against the application's business layer. You need to use the test
project template that meets this requirement. Which template should you use?
A. Web Test Project
B. Load Test Project
C. Unit Test Project
D. Coded Test Project
Answer: C

Microsoft test answers   070-492 certification   070-492 exam   070-492

NO.12 You are developing a WCF service.
A new service instance must be created for each client session.
You need to choose an instancing mode.
Which instance mode should you use?
A. PerCall
B. Single
C. Multiple
D. PerSession
E. PerRequest
Answer: D

Microsoft   070-492 certification training   070-492 test

NO.13 You are developing an ASP .NET MVC application that reads and writes data from a SQL
Server database. You need to maintain data integrity in all situations that use transactions.
A. ReadUncommitted
B. Repeatable
C. Serializable
D. ReadCommitted
Answer: D

Microsoft original questions   070-492   070-492

NO.14 You are developing an ASP .NET MVC application.
Deployment administrators do not have access to Visual Studio 2102, but will have the elevated
permissions required to deploy the application to the servers.
You need to select a deployment tool for use by the deployment administrators.
Which tool should you use?
A. Publish Web Site Tool
B. Web Deployment Package
C. One-Click Publish
D. Deployment Package Editor
Answer: B

Microsoft certification training   070-492   070-492 exam   070-492 original questions   070-492

NO.15 You are developing an ASP .NET MVC application by using Visual Studio 2012.
The application throws and handles exceptions when it runs.
You need to examine the state of the application when exceptions are thrown.
What should you do?
A. From the DEBUG menu in Visual Studio 2012, select Exceptions. Enable the Thrown
check box for Common Language Runtime Exceptions.
B. From the DEBUG menu in Visual Studio 2012, select Exceptions. Disable the User-
unhandled check box for Common Language Runtime Exceptions.
C. Add the following code to the Web.config file of the application.
<customErrors mode="On">
<error statusCode="500" redirect="CustomErrors.html" />
</customErrors>
D. Add the following code to the Web.config file of the application.
<customErrors mode="On" >
<error statusCode="404" redirect="CustomErrors.html"/>
</customErrors>
Answer: A

Microsoft   070-492 original questions   070-492   070-492   070-492 certification training

ITCertKing offer the latest 000-501 exam material and high-quality 646-365 pdf questions & answers. Our 1Y0-250 VCE testing engine and C_FSUTIL_60 study guide can help you pass the real exam. High-quality 000-593 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/070-492_exam.html

74-325 latest Microsoft certification exam questions and answers published

Practice what you preach is the beginning of success. Since you have chosen to participate in the demanding IT certification exam. Then you have to pay your actions, and achieve excellent results. ITCertKing's Microsoft 74-325 exam training materials are the best training materials for this exam. With it you will have a key to success. ITCertKing's Microsoft 74-325 exam training materials are absolutely reliable materials. You should believe that you can pass the exam easily , too.

The person who has been able to succeed is because that he believed he can do it. ITCertKing is able to help each IT person, because it has the capability. ITCertKing Microsoft 74-325 exam training materials can help you to pass the exam. Any restrictions start from your own heart, if you want to pass the Microsoft 74-325 examination, you will choose the ITCertKing.

Maybe on other web sites or books, you can also see the related training materials. But as long as you compare ITCertKing's product with theirs, you will find that our product has a broader coverage of the certification exam's outline. You can free download part of exam practice questions and answers about Microsoft certification 74-325 exam from ITCertKing website as a try to detect the quality of our products. Why ITCertKing can provide the comprehensive and high-quality information uniquely? Because we have a professional team of IT experts. They continue to use their IT knowledge and rich experience to study the previous years exams of Microsoft 74-325 and have developed practice questions and answers about Microsoft 74-325 exam certification exam. So ITCertKing's newest exam practice questions and answers about Microsoft certification 74-325 exam are so popular among the candidates participating in the Microsoft certification 74-325 exam.

Like the real exam, ITCertKing Microsoft 74-325 exam dumps not only contain all questions that may appear in the actual exam, also the SOFT version of the dumps comprehensively simulates the real exam. With ITCertKing real questions and answers, when you take the exam, you can handle it with ease and get high marks.

God is fair, and everyone is not perfect. As we all know, the competition in the IT industry is fierce. So everyone wants to get the IT certification to enhance their value. I think so, too. But it is too difficult for me. Fortunately, I found ITCertKing's Microsoft 74-325 exam training materials on the Internet. With it, I would not need to worry about my exam. ITCertKing's Microsoft 74-325 exam training materials are really good. It is wide coverage, and targeted. If you are also one of the members in the IT industry, quickly add the ITCertKing's Microsoft 74-325 exam training materials to your shoppingcart please. Do not hesitate, do not hovering. ITCertKing's Microsoft 74-325 exam training materials are the best companion with your success.

IT industry is growing very rapidly in the past few years, so a lot of people start to learn IT knowledge, so that keep them for future success efforts. Microsoft 74-325 certification exam is essential certification of the IT industry, many people frustrated by this certification. Today, I will tell you a good way to pass the exam which is to choose ITCertKing Microsoft 74-325 exam training materials. It can help you to pass the exam, and we can guarantee 100% pass rate. If you do not pass, we will guarantee to refund the full purchase cost. So you will have no losses.

Exam Code: 74-325
Exam Name: Microsoft (Administering Office 365 for Small Businesses)
One year free update, No help, Full refund!
Total Q&A: 88 Questions and Answers
Last Update: 2014-02-24

If you are sure that you want to pass Microsoft certification 74-325 exam, then your selecting to purchase the training materials of ITCertKing is very cost-effective. Because this is a small investment in exchange for a great harvest. Using ITCertKing's test questions and exercises can ensure you pass Microsoft certification 74-325 exam. ITCertKing is a website which have very high reputation and specifically provide simulation questions, practice questions and answers for IT professionals to participate in the Microsoft certification 74-325 exam.

74-325 Free Demo Download: http://www.itcertking.com/74-325_exam.html

NO.1 You need to choose an Office 365 subscription plan that provides unlimited mailbox archive
storage space. Which three plans meet the requirements? (Each correct answer presents a
complete solution. Choose three.)
A. Office 365 Enterprise E4
B. Office 365 Midsize Business
C. Exchange Online Plan 1
D. Exchange Online Plan 2
E. Office 365 Enterprise E3
Answer: A,D,E

Microsoft   74-325 pdf   74-325 certification training   74-325 dumps   74-325
Explanation:
D (not C): Exchange Online Plan 2 (but not Exchange Online Plan 1) includes:
Unlimited storage: Take advantage of unlimited storage (50 GB of storage in the user's
primary mailbox, plus unlimited storage in the user's In-Place Archive).

NO.2 Which three criteria can Exchange Online Protection use to block email messages? (Each
correct answer presents a complete solution. Choose three.)
A. ip address
B. language
C. country or region
D. fully qualified domain name (FQDN)
E. email server type
Answer: A,B,C

Microsoft certification training   74-325 dumps   74-325 certification   74-325 certification training
Explanation:
A: Connection filtering
The spam filters first check the IP Allow and IP Block lists and filter inbound messages
according to the specifications of both lists. Messages that are sent from allowed IP
addresses are not subject to further spam filtering; for example, content filtering is
bypassed. Furthermore, messages from an IP address that appears on both lists are
allowed. IP Allow and IP Block lists are empty by default and must be configured by editing
the default connection filter policy.
BC: Content filtering include International Filtering:
You can choose to filter email messages written in specific languages, or sent from specific countries
or regions.

NO.3 Your company has an Office 365 Enterprise El subscription.
You need to remove a user's Microsoft Exchange Online mailbox without removing access to
Microsoft SharePoint Online, Lync Online, Office Professional Plus, or other eligible services.
What should you do?
A. Remove the user's mailbox by running a Windows PowerShell cmdlet.
B. Change the user to an Office 365 E3 subscription.
C. in the Exchange admin center, delete the mailbox.
D. In the Office 365 admin center, remove the Exchange Online license-
Answer: C

Microsoft certification   74-325 demo   74-325 questions   74-325
4. Which three statements about the computer that runs the Windows Azure Active Directory
Sync tool are true? (Each correct answer presents a complete solution. Choose three.)
A. The computer can run Windows Server 2003 Service Pack 2.
B. The computer must run a 64-bit version of Windows.
C. The computer must be joined to the domain or forest that you plan to synchronize with Office
365.
D. The computer must be able to communicate with all domain controllers.
E. The computer must be a domain controller.
Answer: B,C,D

Microsoft answers real questions   74-325   74-325 exam dumps   74-325   74-325
Explanation:
The computer used for Directory Synchronization must meet the following requirements:
-(C, D) It must be joined to the on premise Active Directory. It must be able to connect to
all of the other Domain Controllers (DCs) for all of the forest.
-(not E) It cannot be a domain controller (thus can't be run on SBS).
-(B) It must run on a supported 64 bit Windows Server system which is:
o 64 bit version of Windows Server 2008 R2 SP1 Standard, Enterprise or Datacenter
o 64 bit version of Windows Server 2012 Standard or Datacenter
-It must run Microsoft .NET Framework version 3.5 SP1 and .NET Framework version 4.0
-It must run Windows PowerShell.
-It must be located in an access controlled environment.
Note:
Windows Azure Active Directory Sync tool (DIRSYNC) is an application that provides one
way synchronization from a company's on premise Active Directory (AD) to Windows Azure
Active Directory.
5. Your company plans to permit users to connect their own computers to corporate resources.
You need to prevent specific types of devices from connecting to your Microsoft Exchange
environment.
What should you create?
A. a mail flow rule that prevents mail delivery to the device types
B. an Outlook Web App policy that disables device types
C. a device mailbox policy that denies access to the device types
D. a device access rule that denies access to the device types
Answer: D

Microsoft   74-325 exam simulations   74-325
6. What mailbox data does an IMAP migration process migrate?
A. Contacts
B. All email messages
C. Calendars
D. Only email messages larger than 35 MB
Answer: B

Microsoft   74-325 pdf   74-325   74-325   74-325 certification
7. What does a mobile device mailbox policy allow a Microsoft Exchange Online admin to do?
A. Set criteria for connections to the Exchange Online servers
B. Quarantine devices or allow or block connections based on the device type
C. Provide remote assistance to mobile device users over the Internet
D. Monitor the behavior of users' mobile devices
Answer: A

Microsoft pdf   74-325   74-325 questions   74-325 demo
8. Which three products does Office 365 include? (Each correct answer presents a complete
solution. Choose three.)
A. Microsoft Office Standard
B. Microsoft Lync Online
C. Microsoft Exchange Online
D. Microsoft System Center
E. Microsoft SharePoint Online
Answer: A,B,C

Microsoft certification   74-325   74-325   74-325
Explanation:
"Office 365" refers to subscription plans that include access to Office applications plus other
productivity services that are enabled over the Internet (cloud services), such as Lync web
conferencing and Exchange Online hosted email for business, and additional online storage with
SkyDrive and Skype world minutes for home.
9. Your company has an Office 365 Enterprise E3 subscription for 60 users.
How much Microsoft SharePoint Online storage space does the subscription include?
A. 30 GB
B. 40 GB
C. 60 GB
D. 70 GB
Answer: B

Microsoft test   74-325 exam   74-325
10. How many Microsoft SharePoint Online site collections does the Office 365 Small Business
Premium plan include?
A. 1
B. 2
C. 20
D. 100
Answer: A

Microsoft certification training   74-325 certification training   74-325

ITCertKing offer the latest MSC-235 exam material and high-quality 000-350 pdf questions & answers. Our DC0-260 VCE testing engine and CAT-221 study guide can help you pass the real exam. High-quality 000-283 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/74-325_exam.html