ITCertKing is a website which is able to speed up your passing the IBM certification A2180-188 exams. Our IBM certification A2180-188 exam question bank is produced by ITCertKing's experts's continuously research of outline and previous exam. When you are still struggling to prepare for passing the IBM certification A2180-188 exams, please choose ITCertKing's latest IBM certification A2180-188 exam question bank, and it will brings you a lot of help.
To want to pass IBM A2180-188 certification test can't be done just depend on the exam related books. Instead of blindly studying relevant knowledge the exam demands, you can do some valuable questions. The efficient exam dumps is essential tool to prepare for A2180-188 test. Come on and purchase ITCertKing IBM A2180-188 practice test dumps. This braindump's hit accuracy is high and it works best the other way around. ITCertKing IBM A2180-188 questions and answers are a rare material which can help you pass you exam first time.
ITCertKing exam dumps have two version-PDF and SOFT version which will give you convenient. It is very convenient for you to use PDF real questions and answers. And you can download these materials and print it out for study at any time. The SOFT version simulates the real exam which will give you more realistic feeling. When you are faced with the real exam, you can pass IBM A2180-188 test easily.
Exam Code: A2180-188
Exam Name: IBM (Assessment: IBM WebSphere Lombardi Edition V7.2, BPM Program Management)
One year free update, No help, Full refund!
Total Q&A: 38 Questions and Answers
Last Update: 2014-02-20
As we all know, ITCertKing's IBM A2180-188 exam training materials has very high profile, and it is also well-known in the worldwide. Why it produces such a big chain reaction? This is because ITCertKing's IBM A2180-188 exam training materials is is really good. And it really can help us to achieve excellent results.
A2180-188 Free Demo Download: http://www.itcertking.com/A2180-188_exam.html
NO.1 It is discovered while running Playback 0 that an important but not strictly necessary
sub-process was
missed in the analysis. How should the program manager recommend handling the missed
sub-process?
A. Redo Playback 0 and include the sub process.
B. Note the sub-process as a user story and save it for the next release.
C. Include the sub-process in Playback 1 without validating with the process owner.
D. Schedule a special iteration and playback to address the sub-process after Playback 3.
Answer: B
IBM study guide A2180-188 A2180-188 original questions A2180-188 A2180-188 questions
NO.2 The BPM Program Manager, Process Owner, and Lead Developer are collaborating to
define the theme
and assign user stories for the next iteration. The team is planning the 7th of 15 iterations in
the Release
Plan for Release One. The Program Manager displays a Team Velocity chart showing that
the
Development team has shown significant growth in story points accepted from iterations 1 to
4 and has
been leveling off to roughly 200 story points in iterations 5 and 6.
Given there are 9 iterations remaining in the release plan, the Process Owner immediately
recognizes
there is room for roughly 1800 story points in the remaining time for Release One. However,
the backlog
contains 2400 story points marked as "high" priority and another 1200 story points marked as
"medium"
priority. The Process Owner asks to reduce the points assessed to the high priority user
stories to bring
the total points down to roughly 1800 so as to make them fit in the remaining time. The
Program Manager
agrees.
What is wrong with this scenario.?
A. This is a conversation for a Release Planning meeting and not during Iteration Planning.
B. Team Velocity is fixed and changing the method of estimating story points mid-way
through a release
will not increase the scope of work that can be completed.
C. Process Owner forgot to include a risk factor of 1.4 that should be applied to 1800
resulting in roughly
2500 story points (1.4 x 1800 = 2520) remaining in the Release. No action should be taken.
D. Both "high" and "medium" priority stories should be included in the Release Plan meaning
all user story
points should be reduced by 50% to get all high/medium priority stories to fit in 1800 points
remaining
(2400+1200 = 3600 : 3600/2 = 1800).
Answer: B
IBM study guide A2180-188 certification A2180-188
NO.3 The BPM program manager and process owner for a new hire onboarding process
project need to
ensure that the solution developed by the team will be accepted and adopted by the target
users. To
facilitate this, they decide to:
A. plan additional playbacks for user screens.
B. agree with users to postpone the release until every feature is correct.
C. involve champion SMEs in the discovery and implementation including playbacks.
D. insist on documentation of all user requirements before having the development team
begin work.
Answer: C
IBM A2180-188 exam simulations A2180-188 A2180-188 A2180-188 A2180-188
ITCertKing offer the latest 000-N34 exam material and high-quality M70-301 pdf questions & answers. Our 000-656 VCE testing engine and 1Z1-536 study guide can help you pass the real exam. High-quality 1Y0-A28 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.
Article Link: http://www.itcertking.com/A2180-188_exam.html
没有评论:
发表评论